Project Overview
Steve Bowling Contracting was awarded McBeth Rd Bridge as a standalone element of a 3-year bridge maintenance contract. The original scope of works involved coating applications, steel structure refurbishment and deck replacement of the existing bridge. SBC suggested an alternative design of a full superstructure replacement of the three-span bridge, offering significantly reduced disruption to the 35+ properties serviced by the bridge, greater quality and significantly less ongoing maintenance costs. The alternative solution costs were only a fraction more than the original design due to the fact it could be constructed offsite and installed within 24 hours of the bridge closing.