Project Overview

The project involved construction of the “runway” and approach ramps for one of New Zealand’s largest marine travel lifts for Oceania Marine at Port Whangarei Marine Centre. The project was complex and involved significant temporary works to facilitate construction of the contract works. 20 runway piles were installed to a depth of up to 38m in ground, along with significant precast elements, all completed over water and in the tidal zone. GHK Piling had built the previous travel lift adjacent to the works and were able to call upon their experience to refine and upscale the methodology to make the project a success.