Project Overview
The project was to rectify damage caused by Cyclone Gabrielle and involved Site clearance, subgrade prep. & excavation and the installation of Steel UC Piles (310UC118 grade 350 universal columns 315x307mm >12m) with H4 Timber facing with metalex treatment to cut ends. Works also included concrete for pile encasement, concrete lined channel & subsoil outlet & sigh-rail post foundations. Wall facing & backfilling. Subsoil drains & all environmental controls for works. All work were undertaken within a ‘live’ traffic environment.